Nearing completion,

Roof decking and inner wall structures done, and Cambodian style bamboo-weave finish has gone up on the sealing.

We put shaped rebar in the walls to make it stronger and to make shaping the color of the wall easier, and we have almost finished the front bottle wall.

1507904_732199030137032_1001053508_n

We have also put in the main pluming into the floor of the building, Grey- and black-water is separated! Grey-water can therefore be reused to water the plants in the grey-water-planter, and to flush the toilet with!

1014099_732198790137056_1994605392_n

The grey-water planters have been dug, and connected, and we have started to fill them with gravel and cut off bottles. We have tested the grey-water system by pouring in water, and its working.

1902926_732198636803738_692278517_n

1557446_10152197478461070_1815743767_n

 

1555542_10152197478371070_300304527_n

In the coming week we hope to come close to a finished build, more pictures and updates to come!

3 thoughts on “Nearing completion,

Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>